Citation: | HOU Jie, LI Guo-qing, XIU Guo-lin, HU Nai-lian, QIANG Xing-bang. Optimization of capacity continuity during the deep-area transition for an underground metal mine[J]. Chinese Journal of Engineering, 2023, 45(5): 693-700. doi: 10.13374/j.issn2095-9389.2022.03.24.002 |
[1] |
李國清, 王浩, 侯杰, 等. 地下金屬礦山智能化技術進展. 金屬礦山, 2021(11):1
Li G Q, Wang H, Hou J, et al. Progress of intelligent technology in underground metal mines. Met Mine, 2021(11): 1
|
[2] |
侯正敏, 文長遠, 畢建春. MKTK露天轉地下開采過渡期生產接續方案探討. 世界有色金屬, 2019(15):230 doi: 10.3969/j.issn.1002-5065.2019.15.138
Hou Z M, Wen C Y, Bi J C. Discussion on production succession Scheme during transition period from Open Pit to Underground Mining in MKTK. World Nonferrous Met, 2019(15): 230 doi: 10.3969/j.issn.1002-5065.2019.15.138
|
[3] |
王革民, 陳建宏, 劉浪. 現代礦山開采生產規模優化準則綜述. 礦業研究與開發, 2012, 32(5):1
Wang G M, Chen J H, Liu L. A review on optimization criteria of production scale for modern mine. Min Res Dev, 2012, 32(5): 1
|
[4] |
侯杰, 胡乃聯, 李國清, 等. 多金屬地下礦山生產計劃動態優化. 工程科學學報, 2016, 38(4):453
Hou J, Hu N L, Li G Q, et al. Dynamic optimization of production plans for multi-metal underground mines. Chin J Eng, 2016, 38(4): 453
|
[5] |
章林, 代碧波, 王運敏, 等. 露天礦生產規模優化的經濟動態評估方法—以白云鄂博東介勒格勒鐵礦為例. 金屬礦山, 2018(11):13
Zhang L, Dai B B, Wang Y M, et al. Study on economic dynamic assessment optimization technology of production capacity open-pit mine: A case study of dongjielegele iron mine in Baiyunebo. Met Mine, 2018(11): 13
|
[6] |
Khaboushan A S, Osanloo M. A set of classified integer programming (IP) models for optimum transition from open pit to underground mining methods. Nat Resour Res, 2020, 29(3): 1543 doi: 10.1007/s11053-019-09551-z
|
[7] |
Khaboushan A S, Osanloo M. Semi-symmetrical production scheduling of an orebody for optimizing the depth of transitioning from open pit to block caving. Resour Policy, 2020, 68: 101700 doi: 10.1016/j.resourpol.2020.101700
|
[8] |
King B, Goycoolea M, Newman A. Optimizing the open pit-to-underground mining transition. Eur J Oper Res, 2017, 257(1): 297 doi: 10.1016/j.ejor.2016.07.021
|
[9] |
MacNeil J A L, Dimitrakopoulos R G. A stochastic optimization formulation for the transition from open pit to underground mining. Optim Eng, 2017, 18(3): 793 doi: 10.1007/s11081-017-9361-6
|
[10] |
Bakhtavar E, Abdollahisharif J, Aminzadeh A. A stochastic mathematical model for determination of transition time in the non-simultaneous case of surface and underground mining. J South Afr Inst Min Metall, 2017, 117(12): 1145
|
[11] |
Afum B O, Ben-Awuah E, Askari-Nasab H. A mixed integer linear programming framework for optimising the extraction strategy of open pit - underground mining options and transitions. Int J Min Reclam Environ, 2020, 34(10): 700 doi: 10.1080/17480930.2019.1701968
|
[12] |
Opoku S, Musingwini C. Stochastic modelling of the open pit to underground transition interface for gold mines. Int J Min Reclam Environ, 2013, 27(6): 407 doi: 10.1080/17480930.2013.795341
|
[13] |
Bakhlavar E, Shahriar K, Mirhassani A. Optimization of the transition from open-pit to underground operation in combined mining using (0-1) integer programming. J S Afr N Inst Min Metall, 2012, 112(12): 1059
|
[14] |
Newman A M, Yano C A, Rubio E. Mining above and below ground: Timing the transition. IIE Trans, 2013, 45(8): 865 doi: 10.1080/0740817X.2012.722810
|
[15] |
Whittle D, Brazil M, Grossman P A, et al. Combined optimisation of an open-pit mine outline and the transition depth to underground mining. Eur J Oper Res, 2018, 268(2): 624 doi: 10.1016/j.ejor.2018.02.005
|
[16] |
金鳳英, 崔松, 周玉成. 某礦山露天-地下聯合開采產能銜接方案研究. 中國礦業, 2021, 30(S2): 246
Jin F Y, Cui S, Zhou Y C. Study on capacity connection scheme of open-pit underground combined mining in a mine. China Min Mag, 2021, 30(Sup 2): 246
|
[17] |
李再揚, 王鴻. 露天地下聯合開采的相互影響研究. 礦業研究與開發, 2021, 41(8):12
Li Z Y, Wang H. Study on the interaction between open-pit mining and underground mining. Min Res Dev, 2021, 41(8): 12
|
[18] |
劉懷智, 張洪雷. 黑龍山鐵礦二期露天轉地下開采實踐. 礦業工程, 2021, 19(4):19
Liu H Z, Zhang H L. The practice of open pit mining into underground mining in phase Ⅱ of Heilongshan iron mine. Min Eng, 2021, 19(4): 19
|
[19] |
曾華姣. Dimine三維礦業軟件在露天地下聯合開采中的應用. 世界有色金屬, 2018(2):71
Zeng H J. Dimine 3d mining software application in the open-air underground combined mining. World Nonferrous Met, 2018(2): 71
|
[20] |
Roberts B, Elkington T, van Olden K, et al. Optimising combined open pit and underground strategic plan. Min Technol, 2013, 122(2): 94 doi: 10.1179/1743286313Y.0000000038
|
[21] |
陳忠強, 王李管, 熊書敏, 等. 基于模糊預測性線性規劃的礦山產能分配方案優化分析. 中南大學學報(自然科學版), 2014, 45(9):3166
Chen Z Q, Wang L G, Xiong S M, et al. Optimization analysis of mining capacity allocation scheme based on fuzzy predictive linear programming. J Central South Univ (Sci Technol)
|
[22] |
羅周全, 管佳林, 王益偉, 等. 地下金屬礦山生產規模優化確定方法. 中南大學學報(自然科學版), 2013, 44(7):2875
Luo Z Q, Guan J L, Wang Y W, et al. Production scale optimization determination method of underground metal mine. J Central South Univ (Sci Technol)
|
[23] |
金京男. 線性規劃在礦山穩產方面的利用. 西部探礦工程, 2006, 18(11):57 doi: 10.3969/j.issn.1004-5716.2006.11.031
Jin J N. Application of linear programming in stable production of mines. West China Explor Eng, 2006, 18(11): 57 doi: 10.3969/j.issn.1004-5716.2006.11.031
|
[24] |
徐海. 地下金屬礦山產能優化及開采規劃[學位論文]. 長沙: 中南大學, 2012
Xu H. Optimization of Productivity and Mining Planning in Underground Metal Mines [Dissertation]. Changsha: Central South University, 2012
|